Section 41 Termination of supervision by construction engineerI1

The obligation of the reservoir manager to appoint a construction engineer in respect of the relevant works terminates when the construction engineer gives a copy of the final certificate issued by the engineer in respect of the works to SEPA in accordance with section 39(9).

Annotations

Commencement

I1

S. 41 in force at 1.4.2016 by S.S.I. 2016/42, art. 2, Sch. (with art. 3)