Paragraph 24 I1
England and Wales
From the time when the construction of the tidal works is commenced the undertaker shall proceed with such works with all reasonable diligence and without unreasonable delay until all of the tidal works are completed and all temporary works removed from the river.
Annotations
Commencement
- I1
Sch. 10 para. 24 in force at 26.8.2005, see art. 1