Paragraph 102 I1
England and Wales
If for any reason or in consequence of the construction of any of the works referred to in paragraphs 97 to 99 and 101 any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Thames Water, or there is any interruption in any service provided by Thames Water, the undertaker must—
bear and pay the cost reasonably incurred by Thames Water in making good any damage or restoring the supply; and
make reasonable compensation to Thames Water for any other expenses, loss, damages, penalty or costs reasonably incurred by Thames Water, by reason or in consequence of any such damage or interruption.