Regulation 3 Process to be followed to require a plan to be entered in the SRWRI1

Scotland

(1)

The Commissioner may require a person or a roads authority to enter a plan under section 130A(3) or 130B(2) of the Act in the SRWR by way of a notice entered in the SRWR.

(2)

A notice under paragraph (1) must specify the date by which the recipient of the notice must enter a plan in the SRWR, being a date not less than 30 days and not more than 90 days from the date the notice was entered in the SRWR.

Annotations

Commencement

I1

Reg. 3 in force at 1.4.2023, see reg. 1