Paragraph 1
The works which the undertaker is authorised to construct and maintain by article 3(1) are the following works on the bed of Swansea Bay adjoining the coast between Porthcawl in the County Borough of Bridgend and Port Talbot in the County Borough of Neath Port Talbot and on land within the County Borough of Neath Port Talbot—
-
Work No. 1 — A wind energy electrical generating station consisting of—
- (a)
up to 30 wind turbines generators fixed to the seabed by one or more piles or gravity foundations and extending to a height of up to 130.5 metres above the level of high water, fitted with rotating blades and situated at the following locations—
Wind turbine number Reference point Easting Reference point Northing 1 269103 177986 2 269219 177481 3 269361 176982 4 269828 178465 5 269928 177953 6 270057 177448 7 270214 176951 8 270569 178920 9 270651 178407 10 270763 177901 11 270907 177402 12 271081 176912 13 271368 178982 14 271440 178540 15 271537 178103 16 271660 177672 17 271808 177250 18 271980 176836 19 272167 179040 20 272251 178566 21 272367 178099 22 272516 177641 23 272696 177195 24 272907 176762 25 272657 178920 26 273059 178614 27 273184 178160 28 273344 177716 29 273537 177286 30 273763 176872 - (b)
a network of cables connecting the wind turbines to each other.
- (a)
-
Work No. 2 — A connection between Work No. 1 and Work No. 2A consisting of up to four marine feeder cables along routes commencing by connections with one or more of the wind turbines, then proceeding in a north-easterly direction for 7.22 kilometres until they reach the shore and terminating by a connection with Work No. 2A.
-
Work No. 2A — An extension of the cables comprised in Work No. 2 buried underground, commencing in a junction box at reference point 277406E, 184576N, extending for 121 metres in an easterly direction and terminating in Work No. 3.
-
Work No. 3 — An electrical substation situated at 277527E, 184608N.
-
Work No. 4 — An onshore cable connection with the electrical grid consisting of two electric lines, commencing at Work No. 3 and carried overhead in a north-easterly direction to reference points 278758E, 185469N and 278784E, 185392N, then proceeding underground across the railway sidings and Swansea to London railway and terminating by a connection with the existing electricity pylon.
-
Work No. 5 — A new road providing a construction and maintenance access between Work No. 3 and the road known as the harbour road.