Paragraph 23 Effects of the decisionI1
England and Wales
The decision of the adjudicator shall be binding on the parties, and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement between the parties.
Annotations
Textual amendments
- F1
Sch. Pt. 1 para. 23(1) omitted (W.) (1.10.2011) by virtue of The Scheme for Construction Contracts (England and Wales) Regulations 1998 (Amendment) (Wales) Regulations 2011 (S.I. 2011/1715), regs. 1(1), 3(11) (with reg. 1(2)(3))
- F2
Sch. Pt. 1 para. 23(1) omitted (E.) (1.10.2011) by virtue of The Scheme for Construction Contracts (England and Wales) Regulations 1998 (Amendment) (England) Regulations 2011 (S.I. 2011/2333), regs. 1(1), 3(11) (with reg. 1(2)(3))
Commencement
- I1
Sch. Pt. I para. 23 in force at 1.5.1998, see reg. 1(1)