Paragraph 23 Effects of the decisionI1

England and Wales

F1F2(1)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(2)

The decision of the adjudicator shall be binding on the parties, and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement between the parties.

Annotations

Textual amendments

F1

Sch. Pt. 1 para. 23(1) omitted (W.) (1.10.2011) by virtue of The Scheme for Construction Contracts (England and Wales) Regulations 1998 (Amendment) (Wales) Regulations 2011 (S.I. 2011/1715), regs. 1(1), 3(11) (with reg. 1(2)(3))

F2

Sch. Pt. 1 para. 23(1) omitted (E.) (1.10.2011) by virtue of The Scheme for Construction Contracts (England and Wales) Regulations 1998 (Amendment) (England) Regulations 2011 (S.I. 2011/2333), regs. 1(1), 3(11) (with reg. 1(2)(3))

Commencement

I1

Sch. Pt. I para. 23 in force at 1.5.1998, see reg. 1(1)