Article 4 Amendments to Part 1 (requirements) of Schedule 2
In paragraph 2 of Part 1 (requirements) of Schedule 2—
in sub-paragraph 1(d)—
omit “have a distance of less than 30 metres between the lowest point of the rotating blade of the wind turbine generator and HAT;” and
insert “not used;”
delete sub-paragraph (2) and insert—
“(2)Within Work No. 1A—
(a)The total rotor swept area must not exceed 1.42 square kilometres; and
(b)the total rotor-swept area and the corresponding air gap for each wind turbine generator must accord with the parameters specified below—
Where the Total Rotor-Swept Area is Minimum Air Gap (m) 1.01km2 or less 30 Greater than 1.01km2 and up to 1.13km2 31 Greater than 1.13km2 and up to 1.42km 2 32 ”.
delete paragraph (3) and insert—
“(3)Within Work No. 1B—
(a)The total rotor swept area must not exceed 1.85 square kilometres; and
(b)the total rotor-swept area and the corresponding air gap for each wind turbine generator must accord with the parameters specified below—
Where the Total Rotor-Swept Area is Minimum Air Gap (m) 1.31km2 or less 30 Greater than 1.31km2 and up to 1.47km2 31 Greater than 1.47km2 and up to 1.85km 2 32 ”.