Paragraph 22 Completion of constructionI1

England and Wales

(1)

The undertaker must submit a close out report to the MMO, the MCA, Trinity House, UKHO and the relevant statutory nature conservation body within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following details—

(a)

the final number of installed turbine generators;

(b)

the installed wind turbine generator parameters;

(c)

as built plans;

(d)

latitude and longitude coordinates of the centre point of the location for each wind turbine generator and offshore platform, substation and booster station, provided as Geographical Information System data referenced to WGS84 datum; and

(e)

latitude and longitude coordinates of the in-field cables, provided as Geographical Information System data referenced to WGS84 datum.

(2)

Following completion of construction, no further construction activities can be undertaken under this marine licence.