Paragraph 4 I1

England and Wales

In connection with such Work Nos. 3A to 7A or Work Nos. 3C to 7C and to the extent that they do not otherwise form part of any such work, further associated development within the meaning of section 115(2) (development for which development consent may be granted) of the 2008 Act comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project and which fall within the scope of the work assessed by the environmental statement and the provisions of this marine licence including—

(a)

scour protection around the foundations of the offshore structures;

(b)

cable protection measures such as the placement of rock and/or concrete mattresses, with or without frond devices;

(c)

the removal of material from the seabed required for the construction of Work Nos. 3B to 5B and 7B in scenario 1, 2 or 3 or 3C to 5C and 7C in scenario 4 and the disposal of inert material of natural origin within the Order limits produced during construction drilling, seabed preparation for foundation works, cable installation preparation such as sandwave clearance, boulder clearance and pre-trenching and excavation of horizontal directional drilling exit pits;

(d)

temporary landing places, moorings or other means of accommodating vessels in the construction or maintenance of the authorised project;

(e)

removal of static fishing equipment;

(f)

beacons, fenders and other navigational warning or ship impact protection works;

(g)

disposal of drill arisings in connection with any foundation drilling up to a total of 425 cubic metres; and

(h)

temporary deposit and removal of monitoring equipment.

Annotations

Commencement

I1