Paragraph 6 I1

England and Wales

The undertaker must implement the measures set out in the Sandwich Tern CIMP approved by the Secretary of State, unless otherwise agreed in writing by the Secretary of State in consultation with the relevant statutory nature conservation body and the relevant planning authority. In particular, no operation of any turbine forming part of the authorised development may begin until at least two years after the measures set out in the Sandwich Tern CIMP have been implemented.

Annotations

Commencement

I1

Sch. 17 para. 6 in force at 9.5.2024, see art. 1