Paragraph 14 Fencing and other means of enclosureI1
England and Wales
No phase of the onshore works may commence until details of all proposed permanent fences, walls or other means of enclosure for that phase have been submitted to and approved by the relevant planning authority.
Any approved permanent fencing in relation to Work Nos. 15A or 15B, or in the event of scenario 3 or scenario 4, 15C must be completed before that work is brought into use.
Permanent fencing, walls and other means of enclosure approved under sub-paragraphs (1) and (2) must be provided and maintained until the onshore works to which they relate are decommissioned in accordance with the onshore decommissioning plan approved under requirement 29 (onshore decommissioning).
Annotations
Commencement
- I1
Sch. 2 Pt. 1 para. 14 in force at 9.5.2024, see art. 1