Paragraph 4 I1
England and Wales
Within Work No. 1A, the wind turbine generator foundations must not have—
a total combined seabed footprint (including scour protection) exceeding 483,491 square metres;
a total combined amount of scour protection exceeding 429,770 square metres; or
a total combined volume of scour protection exceeding 1,074,770 cubic metres.
Within Work No. 1B, the wind turbine generator foundations must not have—
a total combined seabed footprint (including scour protection) exceeding 610,726 square metres;
a total combined amount of scour protection exceeding 542,867 square metres; or
a total combined volume of scour protection exceeding 1,357,168 cubic metres.