Regulation 5 Amendment of regulation 4 (meaning of “contract completion date”)
In regulation 4—
in the heading, at the end insert “and “component completion date””;
in paragraph (1)—
omit sub-paragraph (a) (and the “or” at the end);
in sub-paragraph (b), omit “if no such date is described in the contract,”;
in sub-paragraph (c), for “(1)(a) or (b) (as the case may be)” substitute “(1)(b)”;
after paragraph (1) insert—
;(1A)The “component completion date”, in relation to a component of a contract, means—
(a)the date on which the contractor completes all obligations under that component which entitle it to final payment in respect of that component;
(b)if that component is terminated, but any other part of the contract is not terminated, before the date described in sub-paragraph (a), the date on which the component is terminated.
in the opening words of paragraph (2)—
after “(1)(b)” insert “and (1A)(a)”;
after “contract” insert “or in respect of a component”.