Regulation 51 Matters on which the SSRO must give an opinionF1
United Kingdom
The matters relating to a proposed contract which are specified for the purposes of section 35(1)(a) (matters on which the SSRO must give an opinion) are—
where the proposed contract is to be priced using a default pricing method—
the appropriate amount of adjustment that should be made under F2step 2, 3 or 4 of regulation 11;
the appropriate amount of a group cost risk adjustment (regulation 13(2)), the deduction from costs associated with group profits (regulation 13(4)) or group capital servicing adjustment (regulation 13(5));
any question relevant to the cost recovery rates that should be used to estimate likely allowable costs;
the extent to which a particular cost would be an allowable cost;
where the proposed contract is to be priced using an alternative pricing method—
whether the circumstances specified for the use of the alternative pricing method exist;
whether the price has been determined in accordance with the alternative pricing method;
whether any part of the proposed contract should be treated as a component of the contract because the conditions in regulation 9A(1) are met in relation to that part.
The matters relating to a contract which are specified for the purposes of section 35(1)(a) are—
if the contract price were to be re-determined under Part 2 of the Schedule, the matters mentioned in paragraph (1)(a) (read as if a reference to the proposed contract were a reference to the contract);
if the contract price were to be re-determined under Part 4 of the Schedule—
whether the circumstances specified in Part 4 of the Schedule for the re-determination of the contract price exist;
whether the price has been re-determined in accordance with Part 4 of the Schedule or, where the Schedule requires the price to be re-determined using a contract pricing method, in accordance with that contract pricing method;
if the contract is amended so as to add a new component and the price payable under the component is determined in accordance with an alternative pricing method, the matters mentioned in paragraph (1)(b) (read as if a reference to the proposed contract were a reference to the new component);
if the contract price were to be re-determined under the Schedule, the matter mentioned in paragraph (1)(c) (read as if a reference to the proposed contract were a reference to the contract);
whether the Secretary of State has acted reasonably in exercising a power to require the contractor to provide information under regulation 30 (on-demand contract report).
Annotations
Textual amendments
- F1
Reg. 51 substituted (1.4.2024) by The Single Source Contract (Amendment) Regulations 2024 (S.I. 2024/420), regs. 1(2), 39
- F2
Words in reg. 51(1)(a)(i) substituted (5.6.2026) by The Single Source Contract (Amendment) Regulations 2026 (S.I. 2026/510), regs. 1(1), 3(2)