Paragraph 10 Pre-construction
Local mariners, fishermen’s organisations and the UK Hydrographic Office must be notified of any licensed activity or phase of licensed activity through a local Notice to Mariners. A Notice to Mariners must be issued at least 5 days before the commencement of each licensed activity or phase of licensed activity. The MMO and MCA must be sent a copy of the notification within 24 hours of issue. The Notice to Mariners must include—
(a)
the start and end dates for the works;
(b)
a summary of the works to be undertaken;
(c)
the location of the works area, including coordinates in accordance with WGS84; and
(d)
any markings of the works area that will be put in place.