Paragraph 7 Pre-construction
(1)
No licensed activity must commence until a detailed and up-to-date programme of works has been submitted to and approved by the MMO in writing. The programme of works must include—
(a)
a planned timetable for each activity as outlined in paragraphs 4 and 5 of Part 2 of this licence;
(b)
timings for mobilisation of construction plant and for delivery of materials by sea;
(c)
a plan for notifying the MMO of the commencement and cessation of activities and phases of activities; and
(d)
a plan for notifying the MMO of changes to the programme.
(2)
An updated programme of works must be submitted to the MMO in writing every 6 months from the date of approval unless otherwise agreed with the MMO.