Paragraph 7 Pre-construction

Original text. Later amendments are not shown.

(1)

No licensed activity must commence until a detailed and up-to-date programme of works has been submitted to and approved by the MMO in writing. The programme of works must include—

(a)

a planned timetable for each activity as outlined in paragraphs 4 and 5 of Part 2 of this licence;

(b)

timings for mobilisation of construction plant and for delivery of materials by sea;

(c)

a plan for notifying the MMO of the commencement and cessation of activities and phases of activities; and

(d)

a plan for notifying the MMO of changes to the programme.

(2)

An updated programme of works must be submitted to the MMO in writing every 6 months from the date of approval unless otherwise agreed with the MMO.