Section 25 Socially responsible procurement duty: major construction contractsI1
England and Wales
The particular actions mentioned in section 24(5)(b) are—
having regard to model social public works clauses published by the Welsh Ministers under section 27;
in designing and carrying out procedures preceding the award of the major construction contract, considering whether the contract should include social public works clauses;
in negotiating and awarding the contract, taking all reasonable steps—
to include any social public works clauses it considers should be included;
to ensure that clauses included in the contract can be implemented;
in managing the contract, taking all reasonable steps to ensure that any social public works clauses included in the contract are implemented;
(see sections 27 to 31 for further provision about the meaning of “social public works clauses” and their application to major construction contracts).
In this Part, a “major construction contract” is a public contract F1that is a works contract with an estimated value equal to or greater than £2,000,000.
The Welsh Ministers may by regulations amend this section to modify the meaning of a major construction contract.
Annotations
Textual amendments
- F1
Words in s. 25(2) substituted (24.2.2025) by The Procurement (Wales) Regulations 2024 (S.I. 2024/782), regs. 1(2), 46(2) (with reg. 2); S.I. 2024/716, Sch. (as amended by S.I. 2024/959, regs. 1(2), 2(7)(a))
Commencement
- I1
S. 25 not in force at Royal Assent, see s. 48(1)
- I2
S. 25(1) in force at 25.3.2026 by S.I. 2025/1353, art. 2(c)
- I3
S. 25(2)(3) in force at 21.3.2025 by S.I. 2025/338, art. 2(f)