Article 5 Modification of Operating Agreement for Ardingly Reservoir

England and Wales

Until 31st March 2012, Schedule D, paragraph D5.2, of the Agreement Relating to the Maintenance and Operation of the Ardingly Reservoir Scheme dated 30th March 2004 and revised in July 2004f1 is modified to read as follows—

“D5.2.

The Agency may accordingly request that a volume of 200,000m3 be released per annum for the benefit of fisheries or to alleviate a pollution incident. The Company will make the release as requested by the Agency unless prevented from doing so by virtue of an accident or unavoidable operational reasons.”.

Annotations

Footnotes

f1

Available for public inspection at Environment Agency South East, Guildbourne House, Chatsworth Road, Worthing, West Sussex, BN11 1LD.