Paragraph 21 Restoration of land used temporarily for constructionI1
England, Wales and Scotland
Any land used for temporary works and on which subsequent permanent works have not taken place must be reinstated to its condition as at the start of the temporary use, unless otherwise approved by the relevant planning authorities, within 6 months of the completion of commissioning.
Annotations
Commencement
- I1
Sch. 2 para. 21 in force at 23.10.2014, see art. 1