OpenLegislation

Paragraph 5 Detailed design approvalI1

England, Wales and Scotland

(1)

Except for the permitted preliminary works, no authorised development shall commence until written details of the layout, scale and external appearance of the authorised development have been submitted to, and approved by, the relevant planning authorities.

(2)

The details submitted for approval by Pembrokeshire Coast National Park Authority in respect of the key buildings must incorporate the principles and parameters set out in the design principles statement. Such details shall include appropriately scaled plans and sectional drawings indicating existing and proposed finished floor levels, and representations of 3-dimensional images.

(3)

The authorised development must be carried out in accordance with the details approved pursuant to paragraphs (1) and (2) above.

(4)

Development within the Order limits, other than that authorised by reason of this Order, of buildings, plant or any other structures (or part thereof) must not be undertaken such that it results in the erection of buildings, plant or any other structures (or part thereof) above 5 metres in height (as measured from the highest part of the adjacent ground level), without prior approval of the relevant planning authorities.

Annotations

Commencement

I1

Sch. 2 para. 5 in force at 23.10.2014, see art. 1