Paragraph 27 Site visitsI1
England and Wales
The undertaker must, prior to the date of final commissioning of Work No. 4, use reasonable endeavours to facilitate a site familiarisation exercise in connection with Work No. 4 of the authorised development for Lincolnshire Fire and Rescue Service for the purposes of providing the necessary assurance to Lincolnshire Fire and Rescue Service that all the required systems and measures are in place in accordance with the battery safety management plan.
Following the first anniversary of the date of final commissioning of Work No. 4 of the authorised development, the undertaker must use reasonable endeavours to facilitate an annual review of Work No. 4 by Lincolnshire Fire and Rescue Service at the reasonable request of Lincolnshire Fire and Rescue Service, up until the year in which the undertaker commences decommissioning of Work No. 4.