OpenLegislation

Paragraph 12 Construction environmental management planI1

England and Wales

(1)

No part of the authorised development may commence until a construction environmental management plan for that part has been submitted to and approved by the relevant planning authority, such approval to be in consultation with Lincolnshire County Council, as the local highway authority and waste planning authority, the Environment Agency and the Ministry of Defence.

(2)

The construction environmental management plan must be substantially in accordance with the outline construction environmental management plan.

(3)

All construction works associated with the authorised development must be carried out in accordance with the approved construction environmental management plan.

(4)

For the purposes of sub-paragraph (1), “commence” includes part (d) (remedial works in respect of any contamination or other adverse ground conditions) and (i) (Work No. 8 (works to facilitate access to Work Nos. 1 to 7 and 9)) of the permitted preliminary works.

Annotations

Commencement

I1

Sch. 2 para. 12 in force at 30.4.2026, see art. 1