Paragraph 3 Phasing of the authorised development and date of final commissioningI1
England and Wales
The authorised development must not be commenced until a written scheme setting out the phases of construction of the authorised development has been submitted to and approved by the relevant planning authority, such approval to be in consultation with Lincolnshire County Council.
The scheme submitted pursuant to sub paragraph (1) must include a timetable for the construction of the phases of the authorised development and a plan identifying the phasing areas.
The scheme submitted and approved pursuant to sub-paragraph (1) must be implemented as approved.
Nothing shall prevent the undertaker and the relevant planning authority agreeing from time to time to amend the written scheme setting out the proposed phases of construction.
The agreed written scheme may contain flexibility and optioneering for different proposed phases of construction provided that the undertaker notifies the relevant planning authority of the final intended phasing prior to commencement.
Notice of the date of final commissioning with respect to each phase of Work No. 1 must be given to the relevant planning authority within 15 working days of the date of final commissioning for that phase.