Paragraph 175 Arbitration
Save for differences or disputes arising under paragraph 167(2), 167(4), 168(1) and 169, any difference or dispute arising between the undertaker and National Grid Electricity Transmission Plc under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid Electricity Transmission Plc, be determined by arbitration in accordance with article 38 (arbitration).