Article 15 Agreements with street authoritiesI1
England, Wales and Scotland As made
A street authority and the undertaker may enter into agreements with respect to—
the construction, strengthening, improvement, repair or reconstruction of any street including any structure carrying the street over or under the authorised development under the powers conferred by this Order;
the maintenance of the structure of any bridge or tunnel carrying a street over or under the authorised development;
any stopping up, prohibition, restriction, alteration or diversion of a street authorised by this Order;
the adoption by a street authority which is the highway authority of works—
undertaken on a street which is existing public maintainable highway; or
which the undertaker and highway authority agree to be adopted as public maintainable highway; and
such works as the parties may agree.
If such agreement provides that the street authority must undertake works on behalf of the undertaker the agreement may, without prejudice to the generality of paragraph (1)—
make provision for the street authority to carry out any function under this Order which relates to the street in question;
specify a reasonable time for the completion of the works; and
contain such terms as to payment and otherwise as the parties consider appropriate.
Annotations
Commencement
- I1
Art. 15 in force at 13.11.2025, see art. 1
Notes on the whole SI
Textual amendments
- F1
Words in Preamble substituted (6.2.2026) by The Stonestreet Green Solar (Correction) Order 2026 (S.I. 2026/131), art. 1, Sch.