Paragraph 22 Removal of apparatusI1
England, Wales and Scotland
If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or requires that Southern Water’s apparatus is relocated or diverted, that apparatus must not be removed under this Part of this Schedule and any right of Southern Water to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed and is in operation to the reasonable satisfaction of Southern Water in accordance with sub-paragraphs (1) to (8) and until—
any requirement for a permit under the Environmental Permitting (England and Wales) Regulations 2016f1 or other legislation and any other associated consents are obtained, and any approval or agreement required from Southern Water on alternative locations as a result of such re-location are approved, such approvals from Southern Water not to be unreasonably withheld or delayed; and
the undertaker has made the appropriate application required under the Water Industry Act 1991 together with a plan and section of the works proposed and Southern Water has agreed all of the documentation required under the Water Industry Act 1991, such agreement not to be unreasonably withheld or delayed; and such works to be executed only in accordance with the plan, section and description submitted and in accordance with such reasonable requirements as may be made by Southern Water for the alteration or otherwise for the protection of the apparatus, or for securing access to it.
If, for the purpose of executing any works in, on or under any land purchased, held, or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to Southern Water written notice of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order Southern Water reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to Southern Water the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently for the maintenance of that apparatus.
If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, Southern Water must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible use reasonable endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation shall not extend to the requirement for Southern Water to use its compulsory purchase powers to this end unless it elects to do so.
Any alternative apparatus to be constructed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between Southern Water and the undertaker or in default of agreement settled by arbitration in accordance with article 44 (arbitration).
Southern Water must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 44 (arbitration) and after the grant to Southern Water of any such facilities and rights as are referred to in sub-paragraphs (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
Regardless of anything in sub-paragraph (5), if the undertaker gives notice in writing to Southern Water that it desires itself to execute any work, or part of any work in connection with the construction or removal of apparatus in any land controlled by the undertaker, and Southern Water will refer to its own guidance, policies and specifications for carrying out works of that nature, and if agreed by Southern Water (such agreement not to be unreasonably withheld or delayed), that work, instead of being executed by Southern Water, must be executed by the undertaker without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of Southern Water.
Whenever alternative apparatus is to be or is being substituted for existing apparatus, the undertaker will, before taking any steps that will trigger the need for those substitution works, use best endeavours to comply with Southern Water’s reasonable requests for a reasonable period of time to enable Southern Water to—
make network contingency arrangements; or
bring such matters as it may consider reasonably necessary to the attention of end users of the utility in question.
Nothing in sub-paragraph (6) authorises the undertaker to execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) ) within the standoff distances agreed between the parties under sub-paragraph (2) and for the purposes of a sewer or rising main is the standard protective strip which is the strip of land falling 3 metres either side of the sewer or rising main or so as to require any special measures that are outside industry standard measures other than in accordance with paragraph 26 (retained apparatus) below unless otherwise agreed with Southern Water, such agreement not to be unreasonably withheld or delayed, with such provision being brought promptly to the attention of any agent or contractor responsible for carrying out any work on behalf of the undertaker.
Annotations
Commencement
- I1
Sch. 13 para. 22 in force at 13.11.2025, see art. 1