Paragraph 57 CooperationI1

England, Wales and Scotland

(1)

Where in consequence of the proposed construction of any part of the authorised works, the undertaker or National Grid requires the removal of apparatus under paragraph 51(2) (removal of apparatus) or National Grid makes requirements for the protection or alteration of apparatus under paragraph 53 (retained apparatus: protection), the undertaker will use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised works and taking into account the need to ensure the safe and efficient operation of National Grid’s undertaking and National Grid will use its best endeavours to co-operate with the undertaker for that purpose.

(2)

For the avoidance of doubt whenever National Grid’s consent, agreement or approval is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the undertaker, it must not be unreasonably withheld or delayed.

Annotations

Commencement

I1

Sch. 13 para. 57 in force at 13.11.2025, see art. 1

Notes on the whole SI

Textual amendments

F1

Words in Preamble substituted (6.2.2026) by The Stonestreet Green Solar (Correction) Order 2026 (S.I. 2026/131), art. 1, Sch.