OpenLegislation

Paragraph 94 I1

England, Wales and Scotland

The undertaker must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 41 (certification of plans etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail in a format specified by Network Rail.

Annotations

Commencement

I1

Sch. 13 para. 94 in force at 13.11.2025, see art. 1

Notes on the whole SI

Textual amendments

F1

Words in Preamble substituted (6.2.2026) by The Stonestreet Green Solar (Correction) Order 2026 (S.I. 2026/131), art. 1, Sch.