Paragraph 13 Operational noise mitigation and monitoring schemeI1
England, Wales and Scotland As made
Prior to the operation of Work No. 2 or Work No. 3, an ONMMS must be submitted to and approved by the local planning authority.
The ONMMS must—
include details of the plant specification, noise mitigation measures and monitoring procedures; and
demonstrate that, with those noise mitigation measures and monitoring procedures in place, the authorised development is not likely to result in any materially new or materially different noise effects from those assessed in Volume 2, Chapter 14 (Noise) of the environmental statement.
The ONMMS must be implemented as approved.
Annotations
Commencement
- I1
Sch. 2 para. 13 in force at 13.11.2025, see art. 1
Notes on the whole SI
Textual amendments
- F1
Words in Preamble substituted (6.2.2026) by The Stonestreet Green Solar (Correction) Order 2026 (S.I. 2026/131), art. 1, Sch.