Paragraph 2 Closure of storage site by the operator
United Kingdom
The operator must close the storage site where the conditions mentioned in regulation 8(1)(k) are met.
The operator may close the storage site if—
the consent of the authority has been given following an application under sub-paragraph (3), and
any conditions attached to that consent have been met.
An application for the authority's consent to the closure of the storage site must—
be made in writing and sent to the F1Oil and Gas Authority, and
contain the reasons why the operator proposes to close the storage site.
However, a storage site may not be closed under sub-paragraph (1) or (2) until the terms of the post-closure plan have been determined under regulation 13(3).
Annotations
Textual amendments
- F1
Words in Sch. 1 para. 2(3)(a) substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 80; S.I. 2016/920, reg. 2(a)