The Secretary of State for Transport makes the following Regulations in exercise of the powers conferred by sections 74, 97 and 104(1) and (3) of the New Roads and Street Works Act 1991f1:

Annotations to the whole text

Footnotes

f1

1991 c.22. Section 74 was amended by the Transport Act 2000 (c.38), sections 256 and 274, Schedule 31, Part V and by the Traffic Management Act 2004 (c.18), sections 40(4) and 52. The functions of the Secretary of State under sections 74, 97 and 104 are, so far as exercisable in relation to Wales, vested in the Welsh Ministers. Those functions were transferred to the National Assembly for Wales by the National Assembly for Wales (Transfer of Functions) Order 1999 (S.I. 1999/672), article 2, Schedule 1. By virtue of paragraphs 30 and 32 of Schedule 11 to the Government of Wales Act 2006 (c.32), they were transferred to the Welsh Ministers.

Contents

  1. 1Citation, commencement and application
  2. 2Revocation
  3. 3Interpretation
  4. 4Transitional arrangements
  5. 5Application of Regulations
  6. 6Notices
  7. 7Prescribed period
  8. 8Duration of works
  9. 9Prescribed charges
  10. 10Estimates of duration of works
  11. 11Further and revised estimates of duration of works
  12. 12Application of charges and keeping of accounts
  13. 13Offence
  14. 14Form of notice Repealed
  15. 15Service of notices, etc
  16. Signature
  17. Explanatory note

1Citation, commencement and applicationI1

(1)

These Regulations may be cited as the Street Works (Charges for Unreasonably Prolonged Occupation of the Highway) (England) Regulations 2009 and shall come into force on the 6th April 2009.

(2)

These Regulations apply to England only.

2RevocationI1

Subject to regulation 4, the Street Works (Charges for Unreasonably Prolonged Occupation of the Highway) (England) Regulations 2001f1 are revoked.

3InterpretationI1

In these Regulations—

  • “the 1984 Act” means the Road Traffic Regulation Act 1984f1;

  • “the 1991 Act” means the New Roads and Street Works Act 1991;

  • “the 1992 Regulations” means the Street Works (Registers, Notices, Directions and Designations) Regulations 1992f2;

  • “the 2004 Act” means the Traffic Management Act 2004f3;

  • “address”, in relation to a particular method for transmitting an electronic communication, means any number or address used for the purposes of such method of transmission;

  • “bridleway”, F1“carriageway”, “footpath” and “footway” have respectively the meaning given in section 329(1) of the Highways Act 1980f4;

  • F2...

  • “electronic communication” has the meaning given in section 15(1) of the Electronic Communications Act 2000f5;

  • “immediate works” means urgent works or emergency worksf6;

  • “limited designation” means a designation in accordance with regulation 16(3) of the Street Works (Registers, Notices, Directions and Designations) (England) Regulations 2007f7, for particular times or on particular dates;

  • “major works” means—

    1. (a)

      F3. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

    2. (b)

      street works, other than immediate works, where—

      1. (i)

        the street authority has indicated to an undertaker, or

      2. (ii)

        the undertaker considers,

      that an order under section 14 of the 1984 Act (temporary prohibition or restriction on roads) is required; or

    3. (c)

      street works, other than immediate works, the planned duration of which exceeds ten F4working days;

  • “minor works” means F5... street works, other than immediate works or major works, the planned duration of which does not exceed three F6working days;

  • “msa” means million standard axles;

  • “pedestrian planning order” means an order made under section 249(2) or (2A) of the Town and Country Planning Act 1990f8;

  • “permit” and “permit scheme” are to be construed in accordance with section 32 of the 2004 Act;

  • “Permit Authority” means—

    1. (a)

      a F7... highway authority in respect of which an order has been made under section 34(4) of the 2004 Act; or

    2. (b)

      the Secretary of State, as a highway authority or the person with responsibility for the management and control of streets in the Royal Parks, in respect of whom an order has been made under section 35(2) of that Act,

    giving effect to a permit scheme;

  • “prescribed period” means the period prescribed by regulation 7;

  • “remedial works” are works carried out under section 72(3) of the 1991 Act;

  • “road category” means one of the road categories specified in paragraph 1.3.1 of Chapter S1 of the code of practice entitled “Specification for the Reinstatement of Openings in Highways” dated June 2002f9 and approved by the Secretary of State for Transport on 30th June 2002, as revised or re-issued from time to time;

  • “Royal Park” has the meaning given in section 39(1) of the 2004 Act;

  • “standard axle” means an axle which exerts a force of 80 kilo Newtons;

  • “standard works” means ... street works, other than immediate works or major works, the planned duration of which exceeds three F8working days but does not exceed ten working days;

  • “statutory undertaker” means a person entitled by virtue of a statutory right to carry out street works;

  • F9...

  • “traffic order” means an order made under section 1, 6 or 9 of the 1984 Act;

  • “traffic-sensitive street” means a street designated as traffic-sensitive under section 64 of the 1991 Act;

  • “traffic-sensitive time”, in relation to a traffic-sensitive street, means—

    1. (a)

      the times or dates specified in the case of a limited designation; and

    2. (b)

      any time in any other case; and

  • “urgent works”—

    1. (a)

      means street works, other than emergency works, whose execution at the time when they are executed is required (or which the person responsible for the works believes on reasonable grounds to be required)—

      1. (i)

        to prevent or put an end to an unplanned interruption of any supply or service provided by an undertaker;

      2. (ii)

        to avoid substantial loss to an undertaker in relation to an existing service; or

      3. (iii)

        to reconnect supplies or services where an undertaker would be under a civil or criminal liability if the reconnection is delayed until after the expiry of the appropriate notice period; and

    2. (b)

      includes works which cannot reasonably be severed from such works.

4Transitional arrangementsI1

These Regulations do not apply to street works in England in respect of which an undertaker has given notice under section 54(1), 55(1) or 57 of the 1991 Act before the date on which they come into force and the Street Works (Charges for Unreasonably Prolonged Occupation of the Highway) (England) Regulations 2001 shall continue to have effect in relation to those works as if they had not been revoked.

5Application of RegulationsI1

These Regulations apply to every maintainable highway, other than a footpath, a bridleway, a highway in relation to which a pedestrian planning order is in force and a highway whose use by vehicular traffic is prohibited by a traffic order, unless that prohibition is only at particular times.

6NoticesI1

F1(1)

An undertaker executing street works in a highway to which these Regulations apply shall give the highway authority for that highway notice of the beginning of those works not later than—

(a)

in the case of works starting within the period beginning with 12am and ending with 7:59am, 10am on the same day;

(b)

in the case of works starting with the period beginning with 8am and ending with 4:30pm, two hours after the start of the works;

(c)

in the case of works starting with the period beginning with 4:31pm and ending with 11:59pm, 10am on the next day.

F2(2)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F3(3)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(4)

When an undertaker has—

(a)

completed F4interim or permanent reinstatement of a highway;

(b)

removed—

(i)

all signing, lighting and guarding, and

(ii)

all remaining spoil, unused materials and other plant; and

(c)

returned the highway fully to public use,

that undertaker shall give the highway authority notice that this has been done (“works closed notice”) not later than the F5time mentioned in paragraph (5).

F6(5)

The time is—

(a)

in the case of a highway returned fully to public use within the period beginning with 12am and ending with 7:59am, 10am on the same day;

(b)

in the case of a highway returned fully to public use within the period beginning with 8am and ending with 4:30pm, two hours after that full return;

(c)

in the case of a highway returned fully to public use within the period beginning with 4:31pm and ending with 11:59pm, 10am on the next day.

7Prescribed periodI1

In relation to an undertaker executing street works in a highway to which these Regulations apply, the period prescribed under section 74(1)(a) of the 1991 Act shall be two F1working days, starting on the date on which the works begin.

8Duration of worksI1

For the purposes of these Regulations, the duration of street works will only come to an end when the undertaker has—

(a)

completed interim reinstatement, or as the case may be permanent reinstatement, of a highway;

(b)

removed—

(i)

all signing, lighting and guarding, and

(ii)

all remaining spoil, unused materials and other plant; and

(c)

returned the highway fully to public use.

9Prescribed chargesF1

(1)

Subject to paragraphs (2), F2(10), (11) and (12), an undertaker executing street works in a highway to which these Regulations apply shall pay the highway authority a charge to be determined in accordance with paragraphs (3) to (9).

(2)

Paragraph (1) shall not apply to—

(a)

works which do not involve breaking up the street or tunnelling or boring under it, and which take place—

(i)

in a street which is neither a traffic-sensitive street nor a protected street;

(ii)

in the footway of a traffic-sensitive street at a traffic-sensitive time;

(iii)

in the footway of a protected street at any time; or

(iv)

in a traffic-sensitive street, other than at a traffic-sensitive time;

(b)

works consisting only of the creation of holes of less than 3 centimetres in diameter, for investigatory purposes;

(c)

replacing poles, lamp columns or signs in the same location; or

(d)

pole testing.

(3)

Subject to paragraph (7), the charge shall be of an amount calculated in accordance with paragraph (4) or, as the case may be, paragraph (5) and shall be payable for each F3... day, or part of a ... day, by which the duration of the works exceeds the longer of—

(a)

the prescribed period, or

(b)

a reasonable period.

(4)

If, during a period of overrun, the works take place in any part of the carriageway, the amount of the charge, in relation to the description of street in column 2 of an item in column 1 of Table 1, is—

(a)

the amount specified in column 3 of that item for each of the first three F4... days; and

(b)

such further amount as is specified in column 4 of that item for each ... day after that.

Table 1

Charges in relation to works occupying the carriageway during period of overrun.

(1) Item(2) Description of street(3) Amount (£)(each of first three ... days)(4) Amount (£) (each subsequent ... day)
1.Traffic-sensitive street or protected street not in road category 2, 3 or 4.500010000
2.Other street not in road category 2, 3 or 4.25002500
3.Traffic-sensitive street or protected street in road category 2.30008000
4.Other street in road category 2.20002000
5.Traffic-sensitive street or protected street in road category 3 or 4.750750
6.Other street in road category 3 or 4.250250
(5)

If, during a period of overrun, the works do not at any time take place in any part of the carriageway, the amount of the charge, in relation to the description of street in column 2 of an item in column 1 of Table 2, is the amount specified in column 3 of that item.

Table 2

Charges in relation to works outside the carriageway during period of overrun.

(1) Item(2) Description of Street

(3) Amount (£)

(each F5... day)

1.Street not in road category 2, 3 or 4.2500
2.Street in road category 2.2000
3.Street in road category 3 or 4.250
(6)

In this regulation—

  • “description of street” means the description of the street on the date when—

    1. (a)

      the undertaker first gave notice under section 54(1), 55(1) or 57(2) of the New Roads and Street Works Act 1991, or notification under paragraph 2(1)(d) of Schedule 3A to that Act, in respect of the works; or

    2. (b)

      the undertaker first applied for provisional advance authorisation or a permit in respect of the works;

  • “period of overrun” means the part of the duration of the works which exceeds the longer of the prescribed period or a reasonable period; and

  • “provisional advance authorisation” has the same meaning as in the Traffic Management Permit Scheme (England) Regulations 2007.

(7)

The charge will consist of a single payment of £100 in the circumstances set out in paragraph (8) if the requirements of paragraph (9) are met.

(8)

The circumstances referred to in paragraph (7) are that—

(a)

subject to sub-paragraph (c), the undertaker has—

(i)

completed interim reinstatement, or as the case may be permanent reinstatement, of the highway,

(ii)

endeavoured to remove all signing, lighting and guarding, and

(iii)

removed all remaining spoil, unused materials and other plant;

(b)

but for paragraph (c), the duration of the works would not have exceeded the longer of the prescribed period or a reasonable period; and

(c)

not more than five items of signing, lighting or guarding remain on the highway.

(9)

The requirements referred to in paragraph (7) are that—

(a)

the highway authority has—

(i)

informed the undertaker of the identity and location of the items referred to in paragraph (8)(c); and

(ii)

requested the undertaker to remove them; and

(b)

the undertaker has complied with the request by the end of the next F6working day following the date on which the request was received.

(10)

A highway authority may reduce the amount, or waive payment, of a charge—

(a)

in any particular case,

(b)

in such classes of case as they may decide,

(c)

in all cases,

(d)

in all cases other than a particular case, or

(e)

in all cases other than such class of case as they may decide.

(F711)

Charges are only payable in respect of street works where the highway authority has—

(a)

within two working days beginning with the date on which the authority became aware that the works were exceeding the longer of the prescribed period or a reasonable period, given the undertaker a notice informing it that the works are overrunning, and

(b)

not later than three months after receipt of a works closed notice, given the undertaker an account setting out the charges payable.

(F812)

The requirement in paragraph (11)(a) does not apply where the authority becomes aware that the works are exceeding the prescribed period or a reasonable period more than two months after receipt of a works closed notice.

10Estimates of duration of worksI1

(1)

Subject to paragraph (5), if an undertaker has reason to believe that the duration of the works will exceed the prescribed period, that undertaker shall give the highway authority notice containing an estimate of their likely duration—

(a)

in the case of works in connection with the initial placing of apparatus in the street in pursuance of a street works licence, together with the application for the licence;

(b)

in the case of works (not being emergency works) together with—

(i)

the notice under section 55 of the 1991 Act (notice of starting date), or

(ii)

the notification under paragraph 2(1)(d) of Schedule 3A to that Act (notification of proposed works)f1; or

(c)

in the case of emergency works, as soon as reasonably practicable after the works are begun.

(2)

The period of duration contained in a notice given under paragraph (1) shall be taken to be agreed by the authority to be reasonable unless they give written notice to the undertaker, within the relevant period set out in paragraph (3), that they object to the estimate.

(3)

The relevant period referred to in paragraph (2) is—

(a)

5 F1working days, in the case of major or standard works, and

(b)

2 working days, in the case of minor or immediate works,

beginning with the date on which the authority receives the notice containing the estimate.

(4)

A notice of objection given by an authority under paragraph (2) shall contain their own estimate of a reasonable period for the duration of the works.

(5)

This regulation shall not apply where an undertaker proposes to carry out street works in respect of which a permit must be obtained from a Permit Authority.

11Further and revised estimates of duration of worksI1

(1)

Subject to paragraph (4), if it appears to an undertaker that, by reason of matters not previously foreseen or reasonably foreseeable, the duration of the works is likely to exceed—

(a)

the prescribed period,

(b)

the period stated in that undertaker’s previous estimate, or

(c)

the period previously agreed or determined under section 74(2) of the 1991 Act to be a reasonable period,

the undertaker shall give the highway authority written notice containing an estimate or revised estimate.

(2)

Where notice is given under paragraph (1), any previous estimate, agreement or determination shall cease to have effect and the period stated in the new estimate shall be taken to be agreed by the highway authority to be reasonable, unless they give written notice to the undertaker, within the period set out in paragraph (3), that they object to the estimate.

(3)

The period referred to in paragraph (2) shall be 2 F1working days beginning with the date on which the authority received the notice containing the estimate or revised estimate.

(4)

This regulation shall not apply where a permit to carry out proposed street works has been granted by a Permit Authority.

12Application of charges and keeping of accountsI1

(1)

A local highway authority F1and a strategic highways company may deduct from prescribed charges received from an undertaker the reasonable costs of operating the scheme under which they F2or it are paid and shall apply the net proceeds for the purpose of developing or implementing policies for the promotion and encouragement of safe, integrated, efficient and economic transport facilities and services to, from and within their F3or its area.

(2)

A local highway authority F4and a strategic highways company shall keep accounts of sums paid by way of charges.

F5(3)

In this regulation “strategic highways company” means a company for the time being appointed under Part 1 of the Infrastructure Act 2015.

13OffenceI1

An undertaker who, without reasonable cause, fails to give any notice required by these Regulations commits an offence and is liable on summary conviction to a fine not exceeding level 4 on the standard scale.

14Form of noticeF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

15Service of notices, etcF1

(1)

A notice under these Regulations must be given by means of the Department for Transport's digital service for planning and managing roadworks.

(2)

Where a notice cannot be given by that means, it may be given by another means of electronic communication.

(3)

A notice given pursuant to paragraph (2) must be given—

(a)

by sending it to an electronic address which has been agreed with the recipient for that purpose, or

(b)

if there is no such agreement, by sending it to—

(i)

any email address published for the time being by the recipient as an address for contacting the recipient, or

(ii)

if there is no such published address, any email address by means of which the person proposing to send the electronic communication believes, on reasonable grounds, that the notice will come to the attention of any director or other officer of the recipient.

(4)

An electronic communication must be—

(a)

capable of being accessed by the recipient,

(b)

legible, and

(c)

in a form sufficiently permanent to be used for subsequent reference.

(5)

Where a notice cannot be given by another means of electronic communication in accordance with paragraph (3), it may be given by any other means of service agreed between the person giving the notice and the recipient.

(6)

In paragraphs (2) and (5), the reference to not being able to give a notice is a reference to not being able to give it after three attempts.

(7)

Where a notice given under these Regulations notice is successfully given by means of an interface which complies with the Department for Transport's Application Programming Interface (API) specification for planning and managing roadworks, published on 19th December 2019, version 1.12, as revised or re-issued from time to time, the requirement in paragraph (1) is deemed to be met in respect of that notice.

Signature

Signed by authority of the Secretary of State for Transport

Paul Clark

Parliamentary Under Secretary of State

Department for Transport

14th February 2009

Explanatory note

(This note is not part of the Regulations)

These Regulations replace the Street Works (Charges for Unreasonably Prolonged Occupation of the Highway) (England) Regulations 2001 (“the 2001 Regulations”). They provide for the payment of charges to highway authorities where certain street works, executed by undertakers in maintainable highways, are unreasonably prolonged.

Regulation 2 revokes the 2001 Regulations subject to regulation 4 which continues to apply them to street works in England in respect of which notice was given under section 54(1), 55(1) or 57 of the New Roads and Street Works Act 1991 (“the 1991 Act”) before this instrument came into force.

Regulation 6(1) and (2) require an undertaker, executing street works in a highway to which these Regulations apply by virtue of regulation 5, to give an “actual start of works notice” within the periods set out. Regulation 6(3) and (4) specify the period within which a “works clear notice” must be given following the completion of an interim reinstatement of the highway and within which a “works closed notice” must be given following permanent reinstatement.

Regulation 7 establishes the “prescribed period” for the purposes of section 74(1)(a) of the 1991 Act and regulation 8 specifies when works end for the purpose of calculating any overrun charges.

Regulation 9 prescribes the charges payable where the duration of street works exceeds the longer of the prescribed period or a reasonable period, subject to certain exemptions. Different daily rates will apply depending upon the category of street works and the type of street in which they are carried out. Where remedial works are carried out, any overrun will be charged as if those works were in the same category as the works being remedied. For this purpose, provision is made for treating older works as being within contemporary categories of street works. Where the duration of works would not have overrun but for the presence of a single item of signing, lighting or guarding, the charge will consist of a single payment of £100 provided the undertaker removes it within the specified time limit following the highway authority’s request to do so. Provision is made for the reduction or waiver of a charge in various cases.

Regulations 10 and 11, which do not apply where a permit to carry out street works is required, enable an undertaker to provide the highway authority, in certain circumstances, with an estimate or revised estimate of the duration of works, which may be taken to be agreed as a reasonable period in the absence of an objection by the highway authority concerned.

Regulation 12 provides for the application of charges and the keeping of accounts. Regulation 13 creates an offence of failing to give any notice required by the Regulations.

Regulations 14 and 15 prescribe the form of any notice and the manner in which it must be served.

An impact assessment of the effect that this instrument will have on the costs of business and the voluntary sector is available from the Department for Transport, zone 2/08, Great Minster House, 76 Marsham Street, London SW1P 4DR (Tel: 020 7944 8046) and is annexed to the Explanatory Memorandum which is available alongside the instrument on the OPSI website. Both the Explanatory Memorandum and the assessment may also be found by visiting the Department’s website at www.dft.gov.uk.