Regulation 8 Advance notice of worksI1
England and Wales
(1)
For the purposes of section 54, an undertaker shall give not less than three months’ advance notice of major works, except where such works are—
(a)
the subject of a notice under section 55(1) given in accordance with regulation 9(3) and in respect of which no notice has already been given under this paragraph; or
(b)
notified under paragraph 2(1)(d) of Schedule 3A to the 1991 Act.
(2)
For the purposes of section 54(4A), the period prescribed shall be 2 days beginning with the starting date specified in the notice.
(3)
For the purposes of section 54(4B), the period prescribed shall be 15 days.