Regulation 3 Diversionary works executed by an undertaker because of an authority’s major worksI1
England and Wales
Where, because of major works initiated by an authority, an undertaker executes diversionary works, the authority shall pay to the undertaker—
where the major works are major transport works (other than major bridge works or section 86(3) (a) to (g) works) and payment is made in accordance with regulation 8(1), a sum equal to 92.5 per cent. of the allowable costs of the diversionary works;
in other cases where payment is made in accordance with regulation 8(1), a sum equal to 82 per cent. of the allowable costs of the diversionary works;
in all other cases, the allowable costs of the diversionary works.
This regulation is subject to regulation 6.