Part II DESCRIPTION OF PIPE-LINES
| (1) | (2) | (3) | (4) |
|---|---|---|---|
| Route of pipe-lines | Nominal diameter in inches | Date brought into use | |
| From | To | ||
| Beryl B Platform | Beryl A Platform | 20 | 6.7.84 |
| Beryl A Platform | Beryl SPM 2 | 32 | 31.10.88 |
| Beryl A Platform | Beryl SPM 3 | 32 | 31.10.87 |
| Beryl B Platform | Subsea W. I. Well Ness 9/13–31Z | 6 | 16.3.87 |
| Beryl B Platform | Ness subsea Gas Lift Manifold | 6 | 24.9.87 |
| Beryl B Platform | Subsea W. I. Well Beryl 9/13–32 (PP) | 6 | 1.11.87 |
| Beryl B Platform | Subsea W. I. Well 9/13–34 (PU) | 6 | 17.7.88 |
| Beryl B Platform | Subsea Well Beryl 9/13–30 (PV) | 6 | 30.11.87 |
| Subsea Production Well Ness 9/13 – 28A | Beryl B Platform | 6 | 11.8.87 |
| Subsea Production Well Ness 9/13 – 38z (CA) (formally numered 9/13 – 31Z) | Beryl B Platform | 6 | 23.2.88 |