The Sunnica Energy Farm (Correction) Order 2024

S.I. 2024/1154 · Made 12 November 2024

Original text. legislation.gov.uk does not revise statutory instruments, so later amendments are not shown here. Changes made to it are listed under each provision when known.

Infrastructure Planning

Made 12th November 2024

Coming into force 13th November 2024

The Sunnica Energy Farm Order 2024f1 (“the Order”), which granted development consent within the meaning of the Planning Act 2008f2 (“the Act”), contains correctable errors within the meaning of paragraph 1 of Schedule 4 to the Act.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period (as defined in paragraph 1(6)(a) of Schedule 4 to the Act), the Secretary of State received a written request from the applicantf3 for the correction of errors in the Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed East Cambridgeshire District Council and West Suffolk Council as the relevant local planning authoritiesf4, that the request has been received.

The Secretary of State, in exercise of the powers conferred by paragraphs 1(4) and 1(8) of Schedule 4 to the Act, makes the following Order—

Annotations to the whole text

Footnotes

f1

S.I. 2024/802.

f2

2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20) and by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23). There are other amendments to the Act which are not relevant to this Order.

f3

As defined in paragraph 4 of Schedule 4 to the Act.

f4

As defined in paragraph 4 of Schedule 4 to the Act.

Contents

  1. 1Citation and commencement
  2. 2Corrections
  3. Signature
  4. Schedule Corrections
  5. Explanatory note

1Citation and commencement

This Order may be cited as the Sunnica Energy Farm (Correction) Order 2024 and comes into force on 13thNovember 2024.

2Corrections

The Sunnica Energy Farm Order 2024 is corrected as set out in the table in the Schedule to the Order, in which—

(a)

column 1 sets out where the correction is to be made;

(b)

column 2 sets out how the correction is to be made; and

(c)

column 3 sets out the text which is to be substituted, inserted or omitted.

Signature

Signed by authority of the Secretary of State for Energy Security and Net Zero

John Wheadon

Head of Energy Infrastructure Planning Delivery

Department for Energy Security and Net Zero

12th November 2024

Corrections

Column (1)

Where the correction is made

Column (2)

How the correction is made

Column (3)

Text substituted, inserted or omitted

Article 35(2)(d)After “breach”, omit

“of”

Schedule 2, Requirement 6(1)(k)For “/” substitute“or”
Schedule 2, Requirement 6(1)(k)For “Construction and Traffic Management Plan,” substitute“framework construction traffic management plan and travel plan,”
Schedule 8, row: 1-02OmitRow 1-02
Schedule 8, row: 1-03OmitRow 1-03
Schedule 8, row: 5-11OmitRow 5-11
Schedule 8, row: 16-14, column (2)Omit“and access rights”
Schedule 8, row: 16-15, column (2)After “Cable rights”, insert“and access rights”
Schedule 10, row: land and Crown land plans, column (3)For “7”, substitute“6”
Schedule 10, row: land and Crown land plans, column (4)For “30/08/2023”, substitute“30/01/2023”
Schedule 12, paragraph 14(4)For “39”, substitute“38”
Schedule 12, paragraph 99(2)For “(cable works beneath the width of the highway)”, substitute“(streets subject to street works)”

Explanatory note

(This note is not part of the Order)

This Order corrects errors identified in the Sunnica Energy Farm Order 2024, which granted development consent under the Planning Act 2008, following a request made under paragraph 1(5)(a) of Schedule 4 to the Act.