Paragraph 141 Construction liaisonI1

England and Wales

(1)

The undertaker must procure that a dedicated construction liaison officer will throughout the construction of the authorised development on the Campus works area—

(a)

respond to telephone calls and emails from HPUT between 07:00 and 19:00 hours Mondays to Saturdays (and at any time in case of emergencies or for the purposes of paragraphs 138(2)(f) and 139(2) of this Part of this Schedule) in respect of the construction of the authorised development;

(b)

arrange and hold meetings with HPUT no less than once a week (unless otherwise agreed in writing between HPUT and the undertaker) in respect of the construction of the authorised development on the Campus works area throughout the construction of that part of the authorised development; and the officer must issue minutes of each meeting to HPUT no later than 5 working days after each meeting;

(c)

resolve on behalf of the undertaker reasonable concerns raised by HPUT promptly in respect of the construction of the authorised development,

and the undertaker must not construct any part of the authorised development on the Campus works area until it has provided HPUT in writing with the contact details of the officer.

(2)

If HPUT does not consider that the undertaker (or dedicated construction liaison officer on its behalf) has resolved its reasonable concerns in respect of the carrying out of the authorised development pursuant to this paragraph it may require the matter to be settled in accordance with article 38 (arbitration).