Paragraph 19 Water management planI1
England and Wales
No phase of the authorised development may commence until a water management plan for the construction of that phase has been submitted to and approved by the relevant county authority for that phase or, where the phase falls within the administrative areas of both the county of Suffolk and the county of Cambridgeshire, both relevant county authorities, such approval to be in consultation with both relevant planning authorities or the relevant planning authority (as applicable) and the relevant internal drainage board. The water management plan must include—
details as to the management of water use and discharge during construction;
measures to manage surface water runoff during construction;
details as to the drainage system during construction;
details of water quality monitoring during construction;
a spill plan and details for pollution prevention including details on the training and tool box talks; and
roles and responsibilities.
The water management plan must be implemented as approved and maintained throughout the construction of the authorised development.
Annotations
Commencement
- I1
Sch. 2 para. 19 in force at 3.8.2024, see art. 1