Paragraph 3 Phasing of the authorised development and date of final commissioningI1

England and Wales

(1)

No part of the authorised development may commence until a written scheme setting out the phase or phases of construction of the authorised development has been submitted to and approved by both relevant planning authorities.

(2)

The scheme submitted pursuant to sub-paragraph (1) must include a timetable for the construction of the phase or phases of the authorised development.

(3)

The scheme submitted and approved pursuant to sub-paragraph (1) must be implemented as approved and—

(a)

Work No. 2A may not be brought into commercial use without Work No. 1A also being brought into commercial use;

(b)

Work No. 2B may not be brought into commercial use without Work No. 1B also being brought into commercial use; and

(c)

Work No. 2C may not be brought into commercial use without Work No. 1C also being brought into commercial use.

(4)

In respect of the phase or phases, the undertaker must give notice to both relevant planning authorities within seven days of the date of final commissioning that final commissioning of the phase or, where there is more than one phase, each phase has taken place.