Article 2 Interpretation
England and Wales
In this Order, “Schedule 3” (“Atodlen 3”) means Schedule 3 to the Flood and Water Management Act 2010.
For the purposes of this Order, “planning permission” means planning permission under the Town and Country Planning Act 1990 but does not include those permitted developments which are granted planning permission either by virtue of a development order or a local development order in accordance with section 58(1)(a) of that Act.
Annotations
Textual amendments
- F1
Art. 2(3) inserted (9.6.2020) by The Sustainable Drainage (Approval and Adoption) (Wales) (Amendment) Order 2020 (S.I. 2020/517), arts. 1, 3
Marginal citations
- M1
“Construction work” is defined in paragraph 7(2)(a) of Schedule 3.
- M2
“Drainage implications” is defined in paragraph 7(2)(b) of Schedule 3.