Article 5 Compensation for loss resulting from exercise of powers of entry
England and Wales
A developer or other person is entitled to compensation if—
an authorised person enters a construction area or any premises in a construction area in exercise of powers of entry but finds no evidence of a breach of the requirement for approval, and
as a result of the exercise of those powers the developer or other person incurs loss.
If an authorised person enters a construction area or any premises in a construction area in exercise of powers of entry and a breach of the requirement for approval is found, compensation is payable—
to the developer for any loss resulting only from an unreasonable exercise of those powers;
to any other person as if no evidence of a breach were found.
Any claim for compensation must be made to the approving body within 12 months after the exercise of those powers.