Paragraph 1 InterpretationI1
England and Wales
In this Part—
“AEMP” means the Adaptive Environmental Management Plan to be submitted and approved pursuant to Requirement 6;
“authorised development” means the works set out in Parts 1A, 1B and 2 of this Schedule (authorised development, and ancillary and necessary works);
“CEMP” means the Construction Environmental Management Plan to be submitted and approved pursuant to Requirement 5;
“CPTMP” means the construction phase traffic management plan to be submitted and approved pursuant to Requirement 21;
“DCWW” means Dŵr Cymru Cyfyngedig (Company Reference Number: 2366777) whose registered office is at Pentwynn Road, Nelson, Treharris CF46 6LY;
“major event” means an event likely to generate vehicular traffic capable of occupying more than the aggregate number of visitor parking spaces within the authorised development;
“OEMP” means the Operational Environmental Management Plan to be submitted and approved pursuant to Requirement 5;
“operate” means operate the authorised development for generation of electricity for transmission to the national electricity grid following completion of wet commissioning and “operation” and “operating” F1is to be constructed accordingly;
“OPTMP” means the Operational Phase Travel Management Plan to be submitted and approved pursuant to Requirement 22;
“outline Adaptive Environmental Management Plan” means the outline Adaptive Environmental Management Plan dated 25th November 2014 certified as such by the Secretary of State for the purposes of this Order;
“outline Construction Environmental Management Plan” means the outline Construction Environmental Management Plan dated 25th November 2014 certified as such by the Secretary of State for the purposes of this Order;
“outline construction phase traffic management plan” means the outline construction phase traffic management plan annexed to the outline Construction Environmental Management Plan;
“outline Operational Environmental Management Plan” means the outline Operational Environmental Management Plan dated 4th November 2014 certified as such by the Secretary of State for the purposes of this Order;
“outline operational phase traffic management plan” means the outline operational phase traffic management plan submitted with the application certified as such by the Secretary of State for the purposes of this Order.
Annotations
Textual amendments
- F1
Words in Sch. 1 para. 1 substituted (27.10.2015) by The Swansea Bay Tidal Generating Station (Correction) Order 2015 (S.I. 2015/1830), arts. 1, 2, Sch.
Commencement
- I1
Sch. 1 para. 1 in force at 30.6.2015, see art. 1