Paragraph 22 Operational trafficI1
England and Wales
The authorised development must not be operated until F1an OPTMP, substantially in accordance with the outline operational phase traffic management plan, including identification of a travel plan co-ordinator, has been submitted to and approved by the relevant planning authorities.
The approved OPTMP must make provision for the installation of and collection of data from a suitably located automatic traffic counter provided by the undertaker.
The authorised development must be operated in accordance with the approved OPTMP.
Annotations
Textual amendments
- F1
Words in Sch. 1 para. 22(1) substituted (27.10.2015) by The Swansea Bay Tidal Generating Station (Correction) Order 2015 (S.I. 2015/1830), arts. 1, 2, Sch.
Commencement
- I1
Sch. 1 para. 22 in force at 30.6.2015, see art. 1