OpenLegislation

Paragraph 4 Detailed designI1

England and Wales

(1)

The authorised development comprised in Works No. 2b, 2c, 2d, 3, 4, 5a, 7a and 7g, must be carried out in accordance with the relevant works plans and planning drawings in Schedule 7.

(2)

The authorised development seaward of mean low water F1... comprised in Work No. 1a must be carried out in accordance with the relevant works plans and planning drawings in Schedule 7 so far as those drawings refer to works that are within the description of Work No. 1a in F2Part 1A of Schedule 1.

(3)

The authorised development seaward of mean low water F3... comprised in Work No. 1b must be carried out in accordance with the relevant works plans and planning drawings in Schedule 7 so far as those drawings refer to works that are within the description of Work No. 1b in F4Part 1A of Schedule 1.

(4)

The authorised development comprised in Work No. 2a must be carried out in accordance with the relevant works plans and planning drawings in Schedule 7 so far as those drawings refer to works that are within the description of Work No. 2a in F5Part 1A of Schedule 1.

(5)

No authorised development is to commence until the reserved details of the landward parts above mean low water F6... of Works No. 1a and 1b and of all other works referred to in Parts 1A and 1B of Schedule 1 have been submitted to and approved by the relevant planning authorities.

(6)

Where reserved details have been approved by the relevant planning authorities, the authorised development must be carried out in accordance with those details.

(7)

In this Requirement “reserved details” means details of layout, scale, siting, design, dimensions and external appearance.

Annotations

Textual amendments

F1

Word in Sch. 1 para. 4(2) omitted (27.10.2015) by virtue of The Swansea Bay Tidal Generating Station (Correction) Order 2015 (S.I. 2015/1830), arts. 1, 2, Sch.

F2

Words in Sch. 1 para. 4(2) substituted (27.10.2015) by The Swansea Bay Tidal Generating Station (Correction) Order 2015 (S.I. 2015/1830), arts. 1, 2, Sch.

F3

Word in Sch. 1 para. 4(3) omitted (27.10.2015) by virtue of The Swansea Bay Tidal Generating Station (Correction) Order 2015 (S.I. 2015/1830), arts. 1, 2, Sch.

F4

Words in Sch. 1 para. 4(3) substituted (27.10.2015) by The Swansea Bay Tidal Generating Station (Correction) Order 2015 (S.I. 2015/1830), arts. 1, 2, Sch.

F5

Words in Sch. 1 para. 4(4) substituted (27.10.2015) by The Swansea Bay Tidal Generating Station (Correction) Order 2015 (S.I. 2015/1830), arts. 1, 2, Sch.

F6

Word in Sch. 1 para. 4(5) omitted (27.10.2015) by virtue of The Swansea Bay Tidal Generating Station (Correction) Order 2015 (S.I. 2015/1830), arts. 1, 2, Sch.

Commencement

I1

Sch. 1 para. 4 in force at 30.6.2015, see art. 1