OpenLegislation

Paragraph 40 Section 106 agreementI1

England and Wales

(1)

No part of the authorised development is to commence until an agreement pursuant to section 106 of the Town and Country Planning Act 1990 (a “section 106 agreement”) has been secured between The City and F1County of Swansea Council, Neath Port Talbot County Borough Council, AB Ports and the undertaker.

(2)

The section 106 agreement mentioned in sub-paragraph (1) may be altered or varied only with the consent of all of The City and F2County of Swansea Council, Neath Port Talbot County Borough Council, AB Ports and the undertaker.

(3)

The section 106 agreement should reflect that of 8th December 2014, as certified by the Secretary of State.

Annotations

Textual amendments

F1

Word in Sch. 1 para. 40(1) substituted (27.10.2015) by The Swansea Bay Tidal Generating Station (Correction) Order 2015 (S.I. 2015/1830), arts. 1, 2, Sch.

F2

Word in Sch. 1 para. 40(2) substituted (27.10.2015) by The Swansea Bay Tidal Generating Station (Correction) Order 2015 (S.I. 2015/1830), arts. 1, 2, Sch.

Commencement

I1

Sch. 1 para. 40 in force at 30.6.2015, see art. 1