Paragraph 9 Highway worksI1

England and Wales

(1)

No phase of the authorised development affecting an existing public highway is to commence until details of the siting, design and layout of the highway works have after consultation and highway authority for the works in question been submitted to and approved by the relevant planning authority.

(2)

The highway works must be carried out in accordance with the approved details.

(3)

The submitted details are to provide for—

(a)

reinstatement of temporary works upon their completion;

(b)

a site survey to identify pre-existing defects;

(c)

remedy of defects caused during and resulting from the works upon completion; and

(d)

construction of permanent works to adoptable standards.

(4)

In this Requirement “the highway works” means the highway works comprised in F1Work No. 7a.

Annotations

Textual amendments

F1

Words in Sch. 1 para. 9(4) substituted (27.10.2015) by The Swansea Bay Tidal Generating Station (Correction) Order 2015 (S.I. 2015/1830), arts. 1, 2, Sch.

Commencement

I1

Sch. 1 para. 9 in force at 30.6.2015, see art. 1