Paragraph 85 Protection of apparatusI1
England and Wales
Without limiting the other provisions of this Part, before commencing the construction, replacement, renewal or removal of any specified work, and in the case of any specified work of a temporary nature its removal, the undertaker shall submit to the protected person a draft specification.
For the purpose of the preparation of the draft specification and subject to such reasonable stipulations as it may require, the protected person shall as soon as reasonably practicable upon the undertaker’s reasonable request permit the undertaker to have reasonable access to such plans as it may have in its possession and to any of its land or apparatus.
The protected person shall examine the draft specification submitted under sub-paragraph (1) and give its written consent or proposed amendments to the draft specification within 28 days from the date of receipt (and in the event of amendments, the process in this sub-paragraph shall be repeated where those amendments are not accepted) provided that where consent is neither given nor refused within 42 days of the submission of the draft specification (or such other time period agreed by the undertaker and the protected person acting reasonably) consent thereto shall be deemed to have been given. The undertaker shall not commence the specified works until written or deemed consent is provided by the protected person in accordance with this sub-paragraph.
The conditions which may be imposed under any consent and relating to a specification given by the protected person hereunder include conditions as to—
the commencement date and completion date of the specified works;
the reasonable removal, extension or alteration of apparatus necessitated by the specified works;
works for the protection of apparatus necessitated as a result of the specified works;
provision for access to any apparatus;
such works, provisions or methods as are reasonably necessary for the protection of the environment or the protection of the protected person from liability under the terms of any licence relating to its activities; and
an advance warning system providing for liaison between the undertaker and the protected person in respect of potential performance operational issues affecting, or damage to, apparatus arising from the specified works.
The specified works shall be executed only—
in accordance with the specification;
exercising the standard of skill and care reasonably to be expected of a skilled and experienced professional person engaged in undertakings of a similar scope, nature and complexity as the specified works; and
in accordance with such reasonable conditions and requirements as may be imposed by the protected person,
and the protected person shall be entitled to watch and inspect the execution of the specified works.
Nothing in this paragraph shall preclude the undertaker from submitting at any time or from time to time a draft specification to be implemented in substitution of the draft specification previously submitted, and having done so the provisions of this paragraph shall apply to and in respect of the new draft specification, but the substituted draft specification shall not become the specification and may not be carried out without the consent or deemed consent of the protected person.
The undertaker may not be required to comply with sub-paragraph (1) in a case of emergency provided it has complied with paragraph 88, save that the undertaker shall comply with sub-paragraph (3) in so far as is reasonably practicable in the circumstances, after carrying out any specified works to which this sub-paragraph applies.
The undertaker shall be responsible to the protected person for the reasonable expenses (including VAT) incurred by the protected person in, or in connection with, the inspection of the specified works or the apparatus, the protection of any apparatus or temporary works to be undertaken by the protected person (including in respect of examining the draft specification in accordance with sub-paragraph (3)).
Where the protected person has apparatus that will be affected by the specified works (including the outfall), the undertaker shall determine the exact location of apparatus prior to any specified works being carried out by the undertaker.
The undertaker shall not make any trial holes which interfere with any apparatus without the consent of the protected person.
When works for the provision of any new, extended or altered apparatus or any protective work forming part of any such new, extended or altered apparatus, or existing apparatus, have been completed under this Part to the reasonable satisfaction of the protected person, they shall be vested in the protected person forthwith but shall be maintainable by the undertaker until a period of—
in the case of the outfall works, 24 months has elapsed and the protected person or an engineer appointed by the protected person has issued a certificate of final inspection of the new, altered or extended apparatus;
in the case of any other specified works which vest in the protected person in accordance with this paragraph, 12 months has elapsed and the protected person or an engineer appointed by the protected person has issued a certificate of final inspection of the new, altered or extended apparatus.