Article 3 Development consent etc. granted by the OrderI1
England and Wales
Subject to the provisions of this Order and to Schedule 3 (requirements) and Schedule 16 (protective provisions) to this Order the undertaker is granted—
(a)
development consent for the authorised development; and
(b)
consent for the ancillary works;
to be carried out within the Order limits and in accordance with the approved plans.
Annotations
Commencement
- I1
Art. 3 in force at 24.9.2014, see art. 1