Paragraph 8 Scour and Accretion Monitoring and MitigationI1
England and Wales
The licence holder must submit to the MMO for approval a scour and accretion monitoring and mitigation strategy. The MMO will issue their decision in respect of the scour and accretion monitoring and mitigation strategy:
by 30th September 2014; or
within 5 days of the grant of the DCO; or
by the expiry of 20 business days from receipt of the scour and accretion monitoring and mitigation strategy submission to the MMO,
whichever is the latest.
Prior to the commencement of any part of a licensed activity, a scour and accretion monitoring and mitigation plan for that licensed activity shall be prepared by the licence holder in accordance with the agreed scour and accretion monitoring and mitigation strategy in consultation with the MMO, and submitted to the MMO for approval, in accordance with the procedure in Part 3.
The carrying out of any licensed activity shall proceed only in accordance with the agreed scour and accretion monitoring and mitigation plan approved under condition 8(2).
Annotations
Commencement
- I1
Sch. 15 para. 8 in force at 24.9.2014, see art. 1