Paragraph 14 Ground subsidence monitoring scheme in respect of Undertaker’s apparatusI1
England and Wales
No works of the type referred to in paragraphs 10(1) or 11(1) shall commence until a scheme for monitoring ground subsidence (“referred to in this paragraph as the monitoring scheme”) which is capable of interfering with or risking damage to undertaker’s apparatus has been submitted to and approved by the relevant undertaker, such approval not to be unreasonably withheld or delayed.
The ground subsidence monitoring scheme described in sub-paragraph (1) shall set out—
the apparatus which is to be subject to such monitoring;
the extent of land to be monitored;
the manner in which ground levels are to be monitored;
the timescales of any monitoring activities; and
the extent of ground subsidence which, if exceeded, shall require the promoter to submit for undertaker’s approval a ground subsidence mitigation scheme in respect of such subsidence in accordance with sub-paragraph (3).
The monitoring scheme required by sub paragraph (1) and (2) must be submitted within 56 days prior to the commencement of any works authorised by this Order or comprised within the authorised development. Any requirements of the undertaker will be notified within 28 days of receipt of the monitoring scheme. Thereafter the monitoring scheme must be implemented as approved, unless otherwise agreed in writing with the undertaker.
As soon as reasonably practicable after any ground subsidence identified by the monitoring activities set out in the monitoring scheme has exceeded the level described in sub-paragraph (2)(e), a scheme setting out necessary mitigation measures (if any) for such ground subsidence (referred to in this paragraph as a “mitigation scheme”) shall be submitted to the undertaker for approval, such approval not to be unreasonably withheld or delayed; and any mitigation scheme must be implemented as approved, unless otherwise agreed in writing with the undertaker save that the undertaker retains the right to carry out any further necessary protective works for the safeguarding of their apparatus and can recover any such costs in line with paragraph (12).
If the monitoring scheme or mitigation scheme would conflict with any aspect of any ground subsidence monitoring scheme or ground subsidence mitigation scheme approved by the relevant planning authority pursuant to Schedule 3 (requirements) the promoter may submit a revised monitoring scheme or mitigation scheme to the undertaker for its approval, such approval not to be unreasonably withheld or delayed; and the revised monitoring scheme or mitigation scheme must be implemented as approved, unless otherwise agreed in writing with the undertaker.