Paragraph 8 Retained apparatus— protectionI1

England and Wales

(1)

Not less than 56 days before starting the execution of any works authorised by this Order that are near to, or will or may affect, any apparatus (wherever situated) the removal of which has not been required by the promoter under paragraph 7(2), the promoter shall submit to the undertaker a plan.

(2)

In relation to works which will or may be situated over or within 90 metres measured in any direction of, or (wherever situated) may impose any load directly or indirectly upon any apparatus or remove from or impact upon support for any apparatus, the plan to be submitted to the undertaker under sub-paragraph (1) shall be detailed describing—

(a)

the exact position of the works;

(b)

the level at which these are proposed to be constructed or renewed;

(c)

the manner of their construction or renewal;

(d)

the position of all apparatus within 90 metres of the works or upon which the works will or may impose a load or may remove from or affect support for any apparatus;

(e)

by way of detailed drawings, every alteration proposed to be made to any such apparatus

(f)

the proposed programme for carrying out such works; and

(g)

the proposed measure to mitigate the impact of such works on the undertaker’s apparatus.

(3)

The promoter shall not commence the construction or renewal of any works to which subparagraph (2) applies until the undertaker has given written approval of the plan so submitted.

(4)

Any approval of the undertaker required under sub-paragraph (3)—

(a)

may be given subject to reasonable conditions for any purpose mentioned in subparagraph (6); and

(b)

shall not be unreasonably withheld.

(5)

If the undertaker fails to respond to a plan submitted under subparagraph (1) within 35 days of its submission, the promoter may send a written reminder to the undertaker, and if the undertaker has is neither given nor refused its approval within 14 days of the issue of such reminder, such approval it shall be deemed to have been given.

(6)

In relation to a work to which sub-paragraph (2) applies, the undertaker may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its system against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus to enable the safe, efficient and economic operation, maintenance and replacement of such apparatus.

(7)

Works executed under this Order shall be executed only in accordance with the plan, submitted under sub-paragraph (1) (or settled by arbitration in accordance with article 63 (arbitration), as amended from time to time by agreement between the promoter and the undertaker) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (8) by the undertaker for the alteration or otherwise for the protection of the apparatus, or for securing access to it to enable the safe, efficient and economic operation, maintenance and replacement of such apparatus, and the undertaker shall be entitled to watch and inspect the execution of those works.

(8)

Any requirements made by the undertaker under sub-paragraph (7) shall be made within a period of 56 days beginning with the date on which a plan under sub-paragraph (1) is submitted to it.

(9)

If the undertaker, in accordance with sub-paragraph (8) and in consequence of the works proposed by the promoter, reasonably requires the removal of any apparatus and gives written notice to the promoter of that requirement, paragraphs 1 to 3 and 5 to 8 shall apply as if the removal of the apparatus had been required by the promoter under paragraph 7(2).

(10)

Nothing in this paragraph shall preclude the promoter from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of any works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph shall apply to and in respect of the new plan.

(11)

The promoter shall not be required to comply with sub-paragraph (1) in a case of emergency but in that case it shall give to the undertaker notice as soon as is reasonably practicable and a plan of those works as soon as reasonably practicable thereafter and shall comply with sub-paragraph (7) insofar as is reasonably practicable in the circumstances.

Annotations

Commencement

I1

Sch. 16 Pt. 1 Section 3 para. 8 in force at 24.9.2014, see art. 1